What Is PPAP in Manufacturing? How It Works Inside a Supplier Plant

OperaHive teamManufacturing quality specialists
  • Published:
  • Reading time: 9 min read

Expert written and reviewed by the OperaHive team

Add OperaHive as a preferred source on Google

Summarise this article with:

PPAP in manufacturing: a part, its evidence documents and a signed Part Submission Warrant leading to customer approval

Key Takeaways

  • PPAP (Production Part Approval Process) is how a supplier proves to its customer that a part made with production tooling, at production rate, meets every drawing and specification requirement.
  • PPAP is not a quality department task alone. Engineering, production, tool room, purchasing and the lab each own part of the evidence.
  • A new PPAP is needed for new parts and for many changes: design changes, new tooling, a new sub-supplier or material source, a new location or a changed process.
  • Most rejected submissions fail on basics: parts not made on the real process, an out-of-date drawing revision, or a control plan that does not match the shop floor.
  • The approval only stays valid while the process stays the same, so PPAP has to connect with change management after launch.

Introduction

Ask a quality engineer at an automotive supplier what keeps them up before a launch and the answer is often the same: the PPAP in manufacturing sense of the word, a complete package of evidence that the customer will check line by line before releasing a purchase order for production quantities.

Our PPAP guide covers the reference detail: the five submission levels, the 18 elements and the submission steps. This article looks at PPAP from inside the plant. It explains who does what, how the work fits into a launch, what triggers a new submission and how a typical Indian Tier 2 supplier would build one.

What PPAP Means in Plain Terms

The Production Part Approval Process is a standard way for a supplier to show a customer two things: that it has understood every requirement on the design record and specifications, and that its production process can make parts that meet those requirements consistently, at the quoted rate. The method is published by the Automotive Industry Action Group (AIAG); the current manual is the fourth edition.

The output is a PPAP submission: sample parts plus documented evidence such as dimensional results, material and performance test results, the process flow diagram, PFMEA, control plan, MSA studies and initial process capability studies. It is summarised on a single form, the Part Submission Warrant (PSW), which an authorised person at the supplier signs.

PPAP sits at the end of product and process validation in APQP. APQP is the plan for launching a part well; PPAP is the proof that the plan worked.

The customer decides the rules. Each OEM and Tier 1 can add customer-specific requirements, choose the submission level and set its own acceptance criteria. Always read the customer's supplier manual before planning a PPAP.

Who Owns Each Part of a PPAP Inside the Plant

In many plants PPAP is treated as paperwork that the quality engineer assembles at the end. That is why packages arrive late and get rejected. The evidence is created by several teams, and each needs to know its part from the start of the project.

TeamWhat they own in the PPAPTypical evidence
QualityPlans the package, runs the dimensional layout, reviews every element and signs the PSWDimensional results, control plan, PSW, checking aids list
Process / manufacturing engineeringDefines how the part is made and where it can go wrongProcess flow diagram, PFMEA, work instructions
ProductionRuns the trial with production operators, tooling, gauges and cycle timeProduction trial records, sample parts, master sample
Tool room / maintenanceConfirms tooling and fixtures are final, not prototypeTool and fixture records, preventive maintenance plans
Lab / metrologyProves the gauges are capable and runs material and performance testsMSA studies, calibration records, lab test reports
Purchasing / supplier qualityCollects evidence for bought-out material and processesMaterial certificates, sub-supplier PPAPs or approvals
Design (if the supplier owns design)Provides the design record and design risk analysisReleased drawing, DFMEA, design verification results

A simple rule that helps: the person who creates a piece of evidence owns its accuracy, and the quality engineer owns the review. When one person tries to own both, mistakes slip through.

When a PPAP Submission Is Required

A PPAP is needed whenever a new part goes into production, and whenever something changes that could affect the part. The common triggers listed in the AIAG approach and in OEM supplier manuals are:

  • A new part or product
  • An engineering change to the design record, specification or material
  • New, replaced, refurbished or additional tooling, including tooling moved to another location
  • A change of sub-supplier or material source
  • A change to the manufacturing process or method
  • Production at a new or additional site
  • Tooling restarted after being inactive for a long period
  • Correction of a discrepancy found on a previously submitted part

Many of these changes start on the shop floor, not in the design office. A new operator on a critical station, a replacement machine or a different coil supplier can all need customer notification or a new submission. This is why PPAP and 4M change management (man, machine, material, method) need to be linked: the 4M system catches the change, and the PPAP process decides what the customer needs to see.

Worked Example: PPAP for a Machined Bracket at a Pune Supplier

Here is an illustrative example of how the work comes together. A Tier 2 supplier in Pune has won a new steering column bracket from a Tier 1 supplier. The part is a steel pressing followed by CNC machining of two bores. The customer asks for a Level 3 submission: the PSW, sample parts and complete supporting data.

From nomination to PSW: the plant view
  1. 1Kick-offQuality lists every element the customer wants and assigns an owner and date to each.
  2. 2Risk and controlProcess engineering builds the flow diagram, PFMEA and control plan together, so each risk has a control.
  3. 3Gauges readyThe lab completes gauge R&R on the bore gauge and the CMM program before the trial, not after.
  4. 4Production trialProduction runs the trial on the real press, CNC, fixtures and operators at the planned cycle time.
  5. 5Measure and testQuality measures every drawing characteristic on the samples; the lab runs material and hardness tests.
  6. 6CapabilityQuality calculates capability for the special characteristics, here the two bore diameters.
  7. 7Review and signQuality checks each element against the current drawing revision, then signs the PSW.

Two problems typically show up in a project like this. First, the drawing on the shop floor is one revision behind the one in the customer portal, so two dimensions are measured against old tolerances. Second, the PFMEA lists a visual check for burrs, but the control plan on the CNC station does not. Both are found in the internal review because quality compares documents against each other and against the current drawing, not only against a checklist.

The submission goes out with every element traced to the same drawing revision and the same production trial. That traceability is what makes a PPAP easy for the customer to approve and easy to defend in a later audit.

Capability and the Production Trial

Two parts of PPAP cause the most debate on the shop floor: the production trial and the capability study.

  • The production trial must use production tooling, gauges, materials, operators and rate. Parts made on a prototype fixture or hand-finished in the tool room do not prove the process. The AIAG manual sets a default size for this run, but customers often set their own, so confirm the quantity in the customer's requirements.
  • Initial process studies show whether the process is capable on the special characteristics. They are usually reported as Pp and Ppk because the trial is short. Acceptance limits vary by customer and by characteristic, and a process that is stable but not capable needs a reaction plan agreed with the customer.

If capability is low, do not hide it inside the package. Explain the cause, the containment (often 100 percent inspection) and the improvement plan. Customers can work with a known problem; they lose trust when they find an unknown one.

Common PPAP Mistakes in Supplier Plants

  1. Starting the package after the trial. Evidence is then built to fit the parts, not the other way round.
  2. Mismatched documents. The process flow, PFMEA and control plan list different operations or different characteristics.
  3. Wrong drawing revision. Dimensional results do not match the revision on the purchase order.
  4. Gauges not proven. MSA is missing or done on a different gauge from the one used in production.
  5. Sub-supplier gaps. Raw material or heat treatment evidence is missing because nobody asked the sub-supplier in time.
  6. No link to change control. The part is approved, then the process changes quietly and the PPAP no longer describes reality.

Most of these are not technical problems. They are coordination problems between teams, documents and suppliers, which is where a shared system helps more than another spreadsheet.

Managing PPAP with Software

Spreadsheets and shared folders work for one or two PPAPs a year. With many parts, customers and sub-suppliers, the effort goes into chasing files and checking revisions. PPAP software keeps each element with its owner, evidence, reviewer and status, follows the submission level the customer asks for, and lets suppliers upload their own evidence through a portal.

The bigger gain is the connection to other records. When the PFMEA, control plan, MSA, SPC data and change requests sit in the same system as the PPAP, a change to one shows its effect on the others. That is what keeps an approved part approved.

Conclusion

PPAP in manufacturing is the formal proof that a supplier can make the right part, the right way, every time, at the quoted rate. The package is the visible result, but the real work is coordination: every team creating accurate evidence from the real production process, and every document matching the same drawing revision.

Treat PPAP as a plant process with clear owners, start it at kick-off and link it to change management after launch, and approvals come faster and stay valid longer.

Preparing PPAPs in spreadsheets? See how OperaHive tracks every element, owner and approval for your own parts in a free 30-minute demo.

Book a demo
FAQ

Frequently Asked Questions

Still unsure? Ask our team.

What is PPAP in manufacturing?

PPAP (Production Part Approval Process) is the method a supplier uses to show its customer that it understands all design and specification requirements and that its production process can make conforming parts consistently at the quoted rate. It is most common in the automotive supply chain.

Who prepares the PPAP submission?

The quality team usually plans and reviews the package and signs the Part Submission Warrant, but the evidence comes from several teams: process engineering, production, the tool room, the lab and purchasing. Each team should own the accuracy of the evidence it creates.

What is the default PPAP submission level?

Under the AIAG approach, Level 3 is the default unless the customer specifies otherwise. Level 3 means the PSW, sample parts and complete supporting data are submitted to the customer.

Is PPAP required for a process change?

Often, yes. Changes to the manufacturing process, tooling, sub-supplier, material source or production site usually need customer notification and may need a new PPAP. Check the customer's requirements for which changes need a full submission.

What is the difference between APQP and PPAP?

APQP is the planning framework for launching a new part, from concept to production. PPAP is the approval step near the end of APQP that proves the production process meets the customer's requirements.