Key Takeaways
- APQP (advanced product quality planning) is a structured way to launch a new part so it meets customer requirements from the first production run.
- The 5 APQP phases are: plan and define, product design and development, process design and development, product and process validation, and feedback, assessment and corrective action.
- Each phase ends with a gate review, and the outputs of one phase feed the next: the DFMEA feeds the PFMEA, the PFMEA feeds the control plan.
- The APQP process ends with a PPAP submission, so a well-run APQP makes PPAP a matter of collecting evidence that already exists.
- A simple APQP checklist per phase helps the team see what is done, what is late and what is at risk.
Introduction
Launching a new part is risky. The drawing changes, the tooling is late, the first samples fail a dimension and the customer wants an answer by Friday. APQP phases give that chaos a structure: a clear order of work, named owners and checkpoints where the team decides whether the launch is ready to move on.
In this article we explain what APQP is, walk through each of the five phases using one worked example, and finish with an APQP checklist you can use on your next launch. For a deeper look at deliverables and gate reviews, see our complete APQP guide.
What Is APQP?
APQP stands for advanced product quality planning. It is a method, first published by AIAG, for planning a new product and the process that makes it. Most automotive OEMs expect it from their suppliers, and IATF 16949 builds on the same ideas.
The principle is simple: plan quality in before the part is made, instead of inspecting problems out afterwards. A cross-functional team from engineering, quality, manufacturing and purchasing works through the APQP process together, with the customer involved at key points.
Our worked example
To keep things practical, we will follow one launch through every phase: a stamped and welded steel seat bracket that a Tier 2 supplier will make for a Tier 1 seating customer. The bracket has one safety-related characteristic, the weld strength, and a tight hole position that locates the seat frame.
The 5 APQP Phases at a Glance
- 1PlanPlan and define the program
- 2ProductProduct design and development
- 3ProcessProcess design and development
- 4ValidateProduct and process validation
- 5ImproveFeedback, assessment and corrective action
| Phase | Main question | Ends with |
|---|---|---|
| 1. Plan and define | What does the customer need, and can we deliver it? | Agreed goals and a preliminary process flow |
| 2. Product design | Will the design work and can we make it? | Released drawings and a design FMEA |
| 3. Process design | How exactly will we make it? | Process FMEA and a pre-launch control plan |
| 4. Validation | Does the real process make good parts at rate? | Capability results and a PPAP submission |
| 5. Feedback | How do we keep it good and get better? | Lessons learned and lower variation |
The phases overlap. Process design often starts before the product design is fully frozen, which is exactly why each phase needs a clear gate.
Phase 1: Plan and Define the Program
The first phase turns the customer's request into clear goals. The team studies the drawing, the volumes, the timing and the customer-specific requirements, and checks that the business can deliver.
- Typical outputs: design and quality goals, a preliminary bill of materials, a preliminary process flow, a list of preliminary special characteristics and a product assurance plan.
- Who leads: usually the program manager or a quality engineer, with sales and engineering.
Example: for the seat bracket, the team confirms 120,000 parts a year, flags weld strength as a safety characteristic and the locating hole as a key characteristic, and agrees a target of zero customer complaints in the first year.
Phase 2: Product Design and Development
In phase two the design is completed and checked. If the supplier is design-responsible, this is where most of the engineering happens. If the customer owns the design, the supplier still reviews it for manufacturability.
- Typical outputs: a design FMEA, design for manufacturing and assembly reviews, released drawings and specifications, a design verification plan, prototype builds and a prototype control plan.
- Who leads: design engineering, supported by quality and manufacturing.
Example: the DFMEA shows that a thin flange near the weld could crack under load. The team adds a small rib and confirms the change with a prototype load test before the drawing is released.
The FMEA guide explains how to build a DFMEA with the AIAG-VDA method.
Phase 3: Process Design and Development
Phase three designs the manufacturing process that will make the part. Every step from receiving steel to shipping finished brackets is mapped, its risks are analysed and the controls are planned.
- Typical outputs: a process flow diagram, a floor plan, a process FMEA, a pre-launch control plan, work instructions, a packaging plan and an MSA plan.
- Who leads: manufacturing and process engineering, with quality.
Example: the PFMEA rates a wrong weld setting as a high risk. The control plan adds a destructive weld test at every setup and a daily peel test, and a fixture is designed so the bracket cannot be loaded upside down.
Phase 4: Product and Process Validation
Now the real process is proven. The team runs a significant production trial using production tooling, gauges, operators and rate, and checks that the parts are good and the process is capable.
- Typical outputs: a production trial run, measurement system analysis, initial process capability studies, a production control plan, packaging approval and the PPAP submission.
- Who leads: quality, with manufacturing.
Example: the trial run of 300 brackets shows a Cpk of 1.9 on the locating hole and all weld tests pass. The gauge used for the hole passes its Gauge R&R study, and the PPAP is submitted to the customer.
Capability targets and control charts are covered in our SPC and Cpk guide, and the submission itself in the PPAP guide.
Phase 5: Feedback, Assessment and Corrective Action
APQP does not stop at PPAP approval. In the fifth phase the team watches the process in production, reduces variation, responds to customer feedback and records lessons learned for the next launch.
- Typical outputs: reduced variation, customer satisfaction and delivery data, corrective actions and a lessons-learned record.
- Who leads: quality and production.
Example: after three months, SPC shows the hole position drifting as the die wears. The team adds a tool-life limit to the control plan and updates the PFMEA, so the next bracket launch starts with that knowledge built in.
APQP Checklist: What to Confirm in Each Phase
Use this APQP checklist as a starting point. Your customer may ask for more, so always check their specific requirements.
Phase 1 checklist
- Customer requirements, volumes and timing reviewed
- Special characteristics identified
- Preliminary BOM and process flow drafted
- Feasibility confirmed and team named
Phase 2 checklist
- DFMEA completed and actions assigned
- Drawings and specifications released
- Design verification plan agreed
- Prototype parts built and tested
Phase 3 checklist
- Process flow and floor plan approved
- PFMEA completed and linked to the control plan
- Pre-launch control plan and work instructions ready
- Gauges selected and MSA plan agreed
Phase 4 checklist
- Production trial run completed at rate
- MSA and capability studies passed
- Production control plan approved
- PPAP submitted and approved
Phase 5 checklist
- Process performance monitored with SPC
- Customer feedback reviewed
- Corrective actions closed and verified
- Lessons learned recorded for the next launch
Running the APQP Process in Software
On one or two launches, a spreadsheet checklist can work. With several launches in parallel, it becomes hard to see which deliverables are late, whether the control plan still matches the PFMEA, and what is ready for PPAP.
OperaHive APQP software runs each launch through the five APQP phases with owners, due dates and gate reviews. FMEAs and control plans are linked, so a change in one updates the other, and the project flows straight into PPAP software without collecting the evidence twice.
Conclusion
The five APQP phases give every launch the same reliable path: understand the need, design the product, design the process, prove it and keep improving. Each phase builds on the last, and the gates make sure problems are found while they are still cheap to fix.
Start with a clear checklist for each phase, keep your FMEAs and control plans connected, and your PPAP will be ready almost by itself.