PPAP Explained: 5 Levels, 18 Elements and Submission Steps

What the Production Part Approval Process asks for, which elements each level needs, and how to get a package ready without a last-minute rush.

Updated 17 November 2026 · By the OperaHive team

The Production Part Approval Process (PPAP) is how a supplier shows a customer that its manufacturing process can make parts that meet every requirement, consistently and at the quoted rate. It is defined in the AIAG PPAP manual and required by most automotive customers.

A PPAP is not a single document. It is a package of evidence, up to 18 elements, summarised on a Part Submission Warrant (PSW) that the customer approves, approves on an interim basis or rejects.

What is PPAP?

PPAP sits at the end of product and process validation in APQP. After a significant production run on the real line, with the real tooling, operators and gauges, the supplier collects the evidence and submits it.

The customer reviews the package and records a decision. Until the part is approved, the supplier should not ship production parts, unless the customer has granted an interim approval.

The 5 PPAP submission levels

The submission level decides how much of the evidence is sent to the customer and how much is kept on file at the supplier. The customer chooses the level. When nothing is specified, Level 3 is the usual default.

LevelWhat is submitted
Level 1Part Submission Warrant only (and an appearance approval report for appearance items)
Level 2PSW with product samples and limited supporting data
Level 3PSW with product samples and complete supporting data
Level 4PSW and other requirements as defined by the customer
Level 5PSW with product samples and complete supporting data reviewed at the supplier's manufacturing location

Whatever the level, the supplier must keep all applicable elements on file and be able to show them when asked.

The 18 PPAP elements

  1. Design records: the released drawing and specifications, including any customer math data.
  2. Authorized engineering change documents: for changes not yet on the drawing.
  3. Customer engineering approval: where the customer requires it.
  4. Design FMEA: if the supplier is design responsible.
  5. Process flow diagram: every step of the manufacturing process.
  6. Process FMEA: the risks in each process step and their controls.
  7. Control plan: the methods used to control the process and the product.
  8. Measurement system analysis: Gauge R&R and other studies for the gauges in the control plan.
  9. Dimensional results: measurements of every characteristic on the drawing, usually on a ballooned drawing.
  10. Material and performance test results: proof that material and functional requirements are met.
  11. Initial process studies: capability (Ppk) for special characteristics.
  12. Qualified laboratory documentation: the scope and accreditation of the labs used.
  13. Appearance approval report: for parts with appearance requirements.
  14. Sample production parts: taken from the significant production run.
  15. Master sample: a signed sample kept for reference.
  16. Checking aids: fixtures and gauges specific to the part.
  17. Customer-specific requirements: anything extra the customer asks for.
  18. Part Submission Warrant (PSW): the summary document signed by the supplier.

PPAP submission steps

  1. Confirm the requirements. Agree the submission level, the customer-specific requirements and the due date.
  2. Run the significant production run. Use production tooling, gauges, operators and rate. The customer usually defines a minimum run size.
  3. Collect the evidence. Gather each required element and check that it matches the current drawing revision.
  4. Measure the parts. Complete dimensional results for every characteristic and initial capability studies for special characteristics.
  5. Review the package internally. Check every element, every signature and every revision before it goes out.
  6. Sign and submit the PSW. Send the package at the agreed level.
  7. Record the customer decision. Approved, interim approval with an expiry date and actions, or rejected with reasons.

When do you need a new PPAP?

A new or updated submission is usually needed when something about the part or process changes. Common triggers are:

  • A design or specification change.
  • A new or changed material or supplier.
  • New, replaced or refurbished tooling.
  • A move to a different production location or line.
  • A change to the manufacturing process or method.
  • Production restarting after a long break, often twelve months.
  • A correction to a previous nonconformance.

Customers also ask for periodic requalification. Tracking these dates per part is one of the things that quietly slips when PPAP lives in spreadsheets.

Common reasons a PPAP is rejected

  • Documents on different drawing revisions.
  • Dimensional results missing characteristics or using the wrong tolerance.
  • Control plan and PFMEA that do not match.
  • MSA done on a different gauge than the one in the control plan.
  • Capability below the customer's target with no action plan.
  • Missing or unsigned PSW fields.

Managing PPAP in software

OperaHive PPAP software tracks all 18 elements with their evidence and status. Choose the level and the required elements update automatically. Suppliers can upload their own packages through a portal, and every part has its requalification and interim approval dates tracked.

FAQ

Frequently Asked Questions

Still unsure? Ask our team.

What does PPAP stand for?

PPAP stands for Production Part Approval Process. It is the method a supplier uses to show a customer that its production process can make parts that meet all requirements consistently.

What is the default PPAP level?

Level 3 is the usual default when the customer does not specify a level. It requires the PSW, product samples and complete supporting data.

What is a Part Submission Warrant?

The Part Submission Warrant (PSW) is the summary document of a PPAP. The supplier signs it to declare that the parts meet all requirements, and the customer records its approval decision on it.

What is an interim approval?

An interim approval lets the supplier ship parts for a limited time or quantity while open issues are fixed. It always has an expiry date and an action plan, and a full approval is still needed afterwards.

Is PPAP only used in automotive?

PPAP comes from automotive, but other industries use similar approvals. Aerospace uses first article inspection under AS9102 and production part approval under AS9145, and many general manufacturers use a simplified first article process.