What Is Process FMEA (PFMEA)?

Definition

Process FMEA (PFMEA) is a structured analysis of how a manufacturing or assembly process could fail to produce a good part, what the effects would be and which controls prevent or detect each failure.

PFMEA in Simple Terms

A PFMEA takes each step of the process flow diagram and asks what could go wrong there. For every failure mode the team rates severity, occurrence and detection, then plans actions to lower the risk before production starts.

It is the process half of FMEA. The DFMEA covers the design, while the PFMEA assumes the design is correct and looks at how the part is made.

How It Works

The AIAG-VDA FMEA Handbook (2019) sets out seven steps: 1. Planning and preparation: scope, team and timing. 2. Structure analysis: process items, steps and work elements. 3. Function analysis: what each step must achieve. 4. Failure analysis: failure effects, modes and causes. 5. Risk analysis: prevention and detection controls, ratings and Action Priority. 6. Optimisation: actions to reduce risk. 7. Results documentation: record and communicate the outcome.

Older PFMEAs ranked risk with the risk priority number. The controls agreed in the PFMEA flow into the control plan.

Example

At a press-fit station for a bearing, the PFMEA lists "bearing not fully seated" as a failure mode, caused by low press force. Severity is high because the bearing could work loose in service. The team adds force and distance monitoring with automatic rejection, which lowers the detection rating and moves the action priority from high to low.

Why It Matters

  • Process risks are found before tooling is built and parts are shipped.
  • Controls on the line have a clear reason behind them.
  • It is a required PPAP element and a core tool under IATF 16949.

OperaHive FMEA software generates the control plan from the released PFMEA. For more detail, read the FMEA guide.

FAQ

Frequently Asked Questions

Still unsure? Ask our team.

When should a PFMEA be done?

During process design, before tooling and the production control plan are final, and it should be updated whenever the process changes or a new failure is found.

Is RPN still used in PFMEA?

The AIAG-VDA handbook replaced RPN with Action Priority, but some customers and industries still accept or ask for RPN.

What is PFMEA?

PFMEA, or process failure mode and effects analysis, is a structured method to find how a manufacturing or assembly process could fail, what the effects would be and which controls prevent or detect the failure.

What does PFMEA stand for?

PFMEA stands for process failure mode and effects analysis.

What is the difference between DFMEA and PFMEA?

DFMEA looks at how the product design could fail. PFMEA looks at how the process used to make the product could fail. The PFMEA takes special characteristics and severity from the DFMEA.

What is action priority in PFMEA?

Action priority (AP) replaces RPN in the AIAG and VDA FMEA handbook. It rates each risk high, medium or low based on severity, occurrence and detection, with severity weighted most.

What are the steps of a PFMEA?

The AIAG and VDA approach uses seven steps: planning and preparation, structure analysis, function analysis, failure analysis, risk analysis, optimisation and results documentation.

Who should be on a PFMEA team?

A cross-functional team of process or manufacturing engineering, quality, production operators, maintenance and, where useful, design engineering and suppliers.

When should a PFMEA be updated?

Update it when the process, product, equipment or location changes, after customer complaints or internal failures, and when new risks are found. It is a living document.

What is a PFMEA example?

For a press fit step, a failure mode is bearing not fully seated. The effect is noise or early failure, a cause is wrong press force, prevention is a force monitor and detection is a 100 percent height check.

How does PFMEA link to the control plan?

Controls and special characteristics identified in the PFMEA are carried into the control plan, which states how each is measured, how often and the reaction plan. The two should always match.