PPAP in Simple Terms
Before a customer accepts production parts, the supplier collects evidence from a significant production run: measurements, test results, the PFMEA, the control plan, capability and measurement studies. The package is summarised on a Part Submission Warrant.
PPAP is defined in the AIAG PPAP manual (4th edition) and is required under IATF 16949. It is the main output of phase 4 of APQP. Aerospace uses a similar approach under AS9145.
The 5 PPAP Submission Levels
| Level | What is submitted to the customer |
|---|---|
| 1 | Warrant only, plus appearance approval report if required |
| 2 | Warrant with product samples and limited supporting data |
| 3 | Warrant with product samples and complete supporting data (the usual default) |
| 4 | Warrant and other requirements as defined by the customer |
| 5 | Warrant with samples and complete data reviewed at the supplier site |
At every level the supplier keeps all 18 elements on file. The level only decides what is sent.
Example
A supplier moves a die-cast housing to a new machine. This is a process change, so it notifies the customer and runs 300 parts. It measures five parts on every dimension, repeats the capability study on the bore, updates the PFMEA and control plan, and submits a level 3 PPAP. The customer approves before the new machine ships production parts.
When PPAP Is Required
- A new part or product.
- An engineering change to the design or specification.
- A new or changed process, tooling, material or sub-supplier.
- A move to a new site or a tool reactivated after a long break.