Instead of waiting until a part is complete, operators or inspectors measure it while it is still being made. If a dimension drifts, the problem is caught after a few parts rather than after a full batch. It sits between incoming inspection of raw material and final inspection of finished goods.
How It Works
- The control plan states which characteristics to check, at which operation, with which gauge and how often.
- Common points are first-off after setup, periodic checks during the run and last-off before a changeover.
- Results are recorded on a check sheet, an inspection system or a control chart.
- A failed check triggers a reaction plan: stop, contain suspect parts and raise a nonconformance report.
Example
A CNC cell turning shafts checks the bearing diameter on the first part after each tool change and then every 25 parts. At the 75th part the diameter reads close to the upper limit. The operator adjusts the tool offset, the shift leader checks the last 25 parts, and no bad parts move to the grinding operation.
Why It Matters
- Defects are cheaper to fix at the operation that made them.
- Less value is added to parts that will later be scrapped.
- Records show the process was checked as planned, which auditors and customers ask for.