What Is First Article Inspection (FAI)?

Definition

First Article Inspection (FAI) is a complete, documented check of a part made by the production process, confirming that every design requirement on the drawing and specification is met before regular production continues.

FAI in Simple Terms

FAI measures and checks every characteristic on the drawing, not just a sample of key dimensions. It proves that the production process, tooling and materials can make a conforming part. In aerospace, FAI is usually documented to SAE AS9102, and it is part of the requirements of AS9100 suppliers.

Key Elements

AS9102 uses three forms:

  • Form 1, part number accountability: identifies the part and any sub-assemblies.
  • Form 2, product accountability: materials, special processes and functional tests, with supplier and certificate references.
  • Form 3, characteristic accountability: each drawing characteristic, often numbered on a ballooned drawing, with its requirement and the actual result.

A new FAI, or a partial FAI covering the affected characteristics, is normally needed after a design change, a change in manufacturing source, process or location, or a long break in production.

Example

A machine shop starts making an aluminium bracket for an aircraft interior. It balloons 64 characteristics on the drawing, measures each on the first production part, attaches the material certificate and anodising certificate on Form 2, and submits the FAI report to the customer before shipping the first lot.

FAI vs PPAP

FAI is the aerospace approach; automotive uses PPAP, which includes a dimensional report plus capability studies, MSA and a control plan. AS9145 brings PPAP-style approval into aerospace. OperaHive quality inspection software manages incoming, in-process and final inspections.

FAQ

Frequently Asked Questions

Still unsure? Ask our team.

What standard covers first article inspection?

In aerospace, SAE AS9102 defines the FAI requirements and the three standard forms.

When is a new FAI required?

Typically after a design change, a change in process, tooling, location or supplier, or a lapse in production of two years or more as defined in AS9102.

What is FAI in manufacturing?

FAI (first article inspection) is a full, documented check of the first part made from a new or changed production process. It confirms that every drawing characteristic, material and process requirement is met before series production continues.

What is the full form of FAI?

FAI stands for first article inspection. The resulting record is often called a first article inspection report (FAIR).

What is a first article inspection report (FAIR)?

A FAIR is the documented evidence of an FAI. In aerospace it follows the AS9102 format with three forms covering part number accountability, product accountability (materials, special processes) and characteristic accountability.

How do you perform a first article inspection?

Balloon every characteristic on the drawing, measure each one on the first production part, record actual results against tolerances, verify materials and special process certificates, and document any nonconformance before sign-off.

Is FAI part of PPAP?

Yes. In automotive, dimensional results from a full layout inspection are one of the PPAP elements, so FAI style measurement is included. PPAP also requires other evidence such as FMEA, control plans, MSA and capability studies.

Who is responsible for first article inspection?

The manufacturer or supplier producing the part performs and documents the FAI. The customer may review, witness or approve it, and quality engineers usually own the final sign-off.

Is a partial FAI allowed?

Yes. AS9102 allows a partial or delta FAI when only some characteristics are affected by a change, such as a design revision or new tooling. Only the affected characteristics need to be re-verified.

What are common FAI mistakes?

Common mistakes include missing drawing notes or general tolerances from the balloon list, using uncalibrated gauges, skipping material and special process certificates, and not repeating FAI after process changes.

What is first article inspection in aerospace?

In aerospace, FAI is required by AS9100 and documented to the AS9102 standard. It must be repeated after design changes, changes in manufacturing source or process, or a production lapse of two years.

Put First Article Inspection (FAI) Into Practice