Incoming Inspection in Simple Terms
After a goods receipt, material that needs checking is held until inspection is complete. Inspectors review supplier certificates, check labels and quantities, and measure or test a sample against the drawing and the inspection plan. Good material is released; bad material is quarantined.
Common Methods
| Method | When it is used |
|---|---|
| 100 percent inspection | Critical parts, new suppliers or after problems |
| Sampling by AQL | Routine lots, using a sampling plan such as ISO 2859-1 |
| Skip-lot inspection | Suppliers with a proven good record |
| Certificate review only | Low-risk items backed by certificates of conformity |
See Acceptable Quality Limit for how sample sizes and accept numbers are chosen.
Example
A lot of 2,000 machined pins arrives. Under the sampling plan, the inspector measures 125 pins and finds 4 outside the diameter tolerance, which exceeds the accept number. The lot is rejected and quarantined, a nonconformance report is raised, and a SCAR is sent to the supplier.
Why It Matters
- It stops supplier defects before they reach the line or the customer.
- Results feed supplier quality management and vendor rating.
- Inspection effort can be reduced for proven suppliers.