What Is First Pass Yield (FPY)?

Definition

First Pass Yield (FPY) is the percentage of units that complete a process step correctly the first time, without rework, repair or scrap.

FPY in Simple Terms

A process may ship 100 percent good parts, but only because some of them were reworked along the way. FPY counts only the parts that were right first time, so it shows the hidden factory of rework that a final yield figure can hide.

The formula is: FPY = units passing first time / units started. For a line with several steps, multiplying the FPY of each step gives the rolled throughput yield (RTY).

Example

A welding cell starts 500 frames in a shift. 460 pass inspection first time, 30 are reworked and pass, and 10 are scrapped. Final yield is 490 / 500 = 98 percent, but FPY is 460 / 500 = 92 percent. If paint has an FPY of 95 percent, the RTY for the two steps is 0.92 x 0.95, about 87 percent.

FPY vs Other Yield Measures

MeasureWhat it counts
Final yieldGood units out, including reworked ones
First pass yieldGood units without any rework, per step
Rolled throughput yieldProbability a unit passes all steps first time

Why It Matters

  • Rework costs labour, capacity and time, and adds to the cost of poor quality.
  • Low FPY at one step often points to a bottleneck or an unstable process.
  • Tracking FPY by step and by defect type helps target improvement.

OperaHive manufacturing execution system helps teams coordinate work orders and track production output.

FAQ

Frequently Asked Questions

Still unsure? Ask our team.

How do you calculate first pass yield?

Divide the number of units that pass without rework or scrap by the number of units that entered the step, then multiply by 100.

What is a good first pass yield?

It depends on the process, but many mature assembly processes aim for 95 percent or more. The trend over time matters more than a single number.

What is first pass yield in manufacturing?

First pass yield (FPY) is the percentage of units that complete a process step correctly the first time, without rework, repair or scrap. It shows how well a process works before any hidden correction effort.

What does FPY stand for?

FPY stands for first pass yield. It is sometimes called first time yield (FTY) or first time right (FTR), although some companies define these slightly differently.

What is the difference between first pass yield and rolled throughput yield?

First pass yield measures one process step. Rolled throughput yield (RTY) multiplies the FPY of every step in sequence, giving the probability that a unit passes through the whole process without any defect.

What is a first pass yield example?

If 200 parts enter a machining step and 184 pass inspection without rework, first pass yield is 184 divided by 200, which equals 92 percent. Reworked parts that later pass are still excluded.

Why is first pass yield important?

FPY exposes the hidden factory of rework and repair that final yield hides. Improving it reduces scrap cost, shortens lead times and frees capacity without new equipment.

How can you improve first pass yield?

Common approaches include:

  • Root cause analysis on top defect types
  • Error proofing (poka-yoke)
  • Standard work and operator training
  • Statistical process control on key characteristics
  • Better incoming material checks
What is the difference between FPY and final yield?

Final yield counts all good units at the end, including those that were reworked. FPY only counts units that were right the first time, so it is always equal to or lower than final yield.

How do you track first pass yield on the shop floor?

Record units in, units passed first time and units reworked or scrapped at each inspection point, then calculate FPY by shift, line or product. Digital inspection and production records make this automatic and reduce manual tallying errors.