FPY in Simple Terms
A process may ship 100 percent good parts, but only because some of them were reworked along the way. FPY counts only the parts that were right first time, so it shows the hidden factory of rework that a final yield figure can hide.
The formula is: FPY = units passing first time / units started. For a line with several steps, multiplying the FPY of each step gives the rolled throughput yield (RTY).
Example
A welding cell starts 500 frames in a shift. 460 pass inspection first time, 30 are reworked and pass, and 10 are scrapped. Final yield is 490 / 500 = 98 percent, but FPY is 460 / 500 = 92 percent. If paint has an FPY of 95 percent, the RTY for the two steps is 0.92 x 0.95, about 87 percent.
FPY vs Other Yield Measures
| Measure | What it counts |
|---|---|
| Final yield | Good units out, including reworked ones |
| First pass yield | Good units without any rework, per step |
| Rolled throughput yield | Probability a unit passes all steps first time |
Why It Matters
- Rework costs labour, capacity and time, and adds to the cost of poor quality.
- Low FPY at one step often points to a bottleneck or an unstable process.
- Tracking FPY by step and by defect type helps target improvement.