OEE in Simple Terms
An OEE of 100 percent means the machine made only good parts, as fast as possible, with no stops. Real machines lose time to breakdowns, slow running and defects. OEE shows how big those losses are and which type is largest. It is a key measure in TPM.
How to Calculate It
OEE = Availability x Performance x Quality
| Factor | Formula | Losses it captures |
|---|---|---|
| Availability | Run time / planned production time | Breakdowns, setups and adjustments |
| Performance | (Ideal cycle time x total count) / run time | Minor stops and reduced speed |
| Quality | Good count / total count | Scrap, rework and startup rejects |
These three factors map to the "six big losses" used in TPM.
Example
A machine is planned for 480 minutes and has 60 minutes of downtime, so Availability = 420 / 480 = 87.5 percent. The ideal cycle time is 1 minute and it makes 380 parts: Performance = 380 / 420 = 90.5 percent. 361 parts are good: Quality = 361 / 380 = 95 percent. OEE = 0.875 x 0.905 x 0.95 = about 75 percent.
Common Mistakes
- Using a slow "standard" cycle time instead of the true ideal, which inflates performance.
- Leaving setups out of planned time to make availability look better.
- Comparing OEE between very different machines. It is best used to track one asset over time.
- Chasing the 85 percent "world class" figure instead of the largest loss.