AS9145 in Simple Terms
AS9145 was published by SAE International in 2016, based on IAQG work. It brings the launch discipline of automotive APQP and PPAP to aerospace, while fitting the AS9100 family and aerospace practices such as first article inspection.
The 5 Phases
- Planning: customer requirements, risk and project plan.
- Product design and development: design FMEA, design reviews and key characteristics.
- Process design and development: process flow, PFMEA and control plan.
- Product and process validation: measurement system analysis, capability studies, FAI and the PPAP submission.
- Ongoing production, use and post-delivery service: lessons learned and continual improvement.
The standard is supported by the IAQG Supply Chain Management Handbook, which gives forms and guidance for each element.
Example
A supplier taking on a new turbine bracket runs a PFMEA and identifies the bore diameter as a key characteristic. It sets up SPC on the bore, completes an AS9102 FAI and submits a PPAP package with the capability study before rate production starts.
AS9145 vs Automotive APQP
- Phase 5 covers in-service use, reflecting long aerospace product lives.
- FAI to AS9102 is part of the PPAP evidence.
- Requirements apply mainly when the customer flows them down in the contract.