What Is Engineering Change Notice (ECN)?

Definition

An Engineering Change Notice (ECN) is the document that formally releases an approved change to a product, drawing or BOM and tells every affected team what has changed and when it takes effect.

ECN in Simple Terms

Change usually starts with an engineering change request that proposes a change. Once the change is reviewed and approved, the ECN is issued to put it into effect. It tells purchasing, production, quality and suppliers exactly what is changing and from which date, lot or serial number. Some companies call it an engineering change order (ECO).

ECR vs ECN

ECRECN
PurposePropose and justify a changeRelease an approved change
TimingBefore approvalAfter approval
Key contentProblem, reason, proposed solutionAffected items, new revisions, effectivity

Key Elements and Example

  • ECN number and link to the originating ECR.
  • Affected parts, drawings and BOMs with old and new revisions.
  • Effectivity: date, lot or serial number.
  • Disposition of existing stock and work in progress.
  • Approvals and distribution list.

An ECN releases revision E of a bracket drawing with a thicker flange. It states that the change applies from production order 4521, that existing revision D stock can be used up, and that the PPAP must be resubmitted to the customer before shipment.

Why It Matters

Without a clear ECN, some teams keep working to the old revision. In automotive, product changes usually need customer notification and may need a new PPAP. OperaHive engineering change management handles change requests and notices, BOM revisions, approvals and impact reviews.

FAQ

Frequently Asked Questions

Still unsure? Ask our team.

Is an ECN the same as an ECO?

Many companies use the terms interchangeably. Where both exist, the ECO is the instruction to make the change and the ECN is the notice to affected parties.

Who issues an ECN?

Engineering or the change control team usually issues it after the change has been approved by the change board.

What is an engineering change notice (ECN)?

An engineering change notice is a document that announces an approved change to a product or its documents and tells affected teams what is changing, why and when it takes effect.

What is ECN full form?

ECN stands for engineering change notice, sometimes called engineering change notification. It follows an approved engineering change request in the change process.

What is the difference between ECR and ECN?

An ECR, or engineering change request, proposes a change and starts the review. The ECN is issued after approval to communicate and put the change into effect.

What should an ECN include?

An ECN typically includes:

  • ECN number and date
  • parts and documents affected
  • description and reason for change
  • before and after revisions
  • effectivity date or serial number
  • disposition of existing stock
  • approvals
What is ECN effectivity?

Effectivity defines when the change applies, such as a date, serial number or lot. It tells production and purchasing exactly which product is built to the old version and which to the new.

What is an ECN example?

Engineering changes the wall thickness of a bracket to fix cracking. The ECN lists the new drawing revision, sets effectivity from the next lot, says to use up old stock for spares and notifies purchasing and production.

Does an ECN require customer approval?

It depends on the change and customer requirements. In automotive and aerospace, changes to form, fit, function or process often need customer notification or approval before the ECN takes effect.

What are common ECN mistakes?

Common mistakes include unclear effectivity, missing affected documents, no plan for existing stock and not updating the BOM, FMEA and control plan at the same time.