ECN in Simple Terms
Change usually starts with an engineering change request that proposes a change. Once the change is reviewed and approved, the ECN is issued to put it into effect. It tells purchasing, production, quality and suppliers exactly what is changing and from which date, lot or serial number. Some companies call it an engineering change order (ECO).
ECR vs ECN
| ECR | ECN | |
|---|---|---|
| Purpose | Propose and justify a change | Release an approved change |
| Timing | Before approval | After approval |
| Key content | Problem, reason, proposed solution | Affected items, new revisions, effectivity |
Key Elements and Example
- ECN number and link to the originating ECR.
- Affected parts, drawings and BOMs with old and new revisions.
- Effectivity: date, lot or serial number.
- Disposition of existing stock and work in progress.
- Approvals and distribution list.
An ECN releases revision E of a bracket drawing with a thicker flange. It states that the change applies from production order 4521, that existing revision D stock can be used up, and that the PPAP must be resubmitted to the customer before shipment.
Why It Matters
Without a clear ECN, some teams keep working to the old revision. In automotive, product changes usually need customer notification and may need a new PPAP. OperaHive engineering change management handles change requests and notices, BOM revisions, approvals and impact reviews.