What Is Deviation?

Definition

A deviation is a written, approved permission to depart from a specified requirement, such as a drawing dimension, material or process step, for a limited quantity of parts or a limited time.

Deviation in Simple Terms

Sometimes a plant knows in advance that it cannot meet a requirement exactly. A material may be out of stock, a machine may be down, or a supplier may ship a part with a minor issue. A deviation is the formal way to ask the owner of the requirement, often the customer or design authority, for permission to proceed anyway.

The key point is that a deviation is temporary and controlled. It names the parts, the quantity or date range, the reason and the risk assessment. When it expires, the original requirement applies again. Some companies call a deviation raised before production a "deviation permit" and one raised after the fact a "concession" or "waiver".

Deviation vs Nonconformance

DeviationNonconformance (NCR)
TimingUsually requested before the work is doneRaised after a defect is found
PurposePermission to depart from a requirementRecord and disposition of a defect
ScopeLimited quantity or time periodThe specific affected parts

When a nonconformance report is given a "use as is" disposition, it often needs customer approval in the same way a deviation does.

Example

A machining supplier runs short of the specified bar stock grade. Engineering confirms an equivalent grade with the same strength, and the customer approves a deviation for 2,000 shafts over four weeks. Each lot is labelled with the deviation number so the parts stay traceable.

Common Mistakes

  • Using deviations as a permanent fix instead of raising an engineering change request.
  • Shipping before the customer has signed the approval.
  • Not marking affected parts, which breaks traceability.
  • Letting deviations expire without checking whether the root cause was fixed.

With OperaHive quality inspection software, teams can record nonconformances and follow the corrective actions linked to them.

FAQ

Frequently Asked Questions

Still unsure? Ask our team.

What is the difference between a deviation and a waiver?

Terms vary by company, but a deviation is usually approved before the work is done, while a waiver or concession accepts parts that were already made outside the requirement.

Who approves a deviation?

The owner of the requirement approves it. For customer drawings and specifications that is normally the customer, with internal sign-off from quality and engineering.

What is a deviation in manufacturing?

A deviation is a formally approved, temporary permission to make or ship product that does not fully meet a specified requirement. It is limited by quantity, time or lot and has a clear end point.

What is a deviation in quality management?

In quality management, a deviation is any departure from an approved procedure, specification or instruction. A planned deviation is approved in advance; an unplanned one is investigated like a nonconformance.

What is a deviation example?

A supplier cannot get the specified grade of steel for two weeks. Engineering confirms an alternative grade is suitable, the customer approves a deviation for 5,000 parts, and the lots are labelled and tracked.

What should a deviation request include?

A deviation request should include:

  • the requirement affected
  • what will differ and why
  • the quantity, lots or time period
  • risk assessment and test evidence
  • how parts will be identified
  • required approvals
Deviation vs nonconformance: what is the difference?

A nonconformance is a failure to meet a requirement that is found after it happens. A deviation is a deliberate, approved and time-limited departure from a requirement.

Deviation vs engineering change: what is the difference?

A deviation is temporary and ends after a set quantity or date. An engineering change permanently updates the drawing or specification. Repeated deviations for the same issue usually mean an engineering change is needed.

How long does a deviation last?

Only as long as the approved quantity, lots or time period. Once that limit is reached, the deviation expires and the original requirement applies again.

What are common mistakes with deviations?

Common mistakes include shipping before approval, using deviations to avoid fixing root causes, poor labelling of deviated parts and letting deviations run past their expiry date.