The Complete Guide to APQP: 5 Phases, Deliverables and Gate Reviews

What Advanced Product Quality Planning asks for, phase by phase, and how to run it so the launch reaches PPAP with the evidence already in place.

Updated 17 November 2026 · By the OperaHive team

Advanced Product Quality Planning (APQP) is the structured way automotive suppliers plan a new part, from the first customer enquiry to stable production. It was published by AIAG and is expected by most automotive OEMs, and IATF 16949 builds on it.

The idea is simple: plan quality in before the part is made, rather than inspect problems out afterwards. In practice APQP is a set of deliverables, owned by a cross-functional team, checked at gate reviews and closed out with a PPAP submission.

What is APQP?

APQP is a framework for developing a product and the process that makes it. It defines what has to be done, by whom and by when, so that the customer receives parts that meet every requirement from the first production run.

A typical APQP project brings together engineering, quality, manufacturing, purchasing and the customer. Each phase produces outputs that feed the next one: the design FMEA feeds the process FMEA, the process FMEA feeds the control plan, and the control plan drives what is measured during the production trial run.

APQP is not only for automotive. Aerospace suppliers use a very similar approach under AS9145, and many general manufacturers use a lighter version for new product introduction.

The 5 phases of APQP

APQP is usually shown as five overlapping phases. Work in one phase often starts before the previous one is fully closed, which is why clear gates matter.

PhasePurposeTypical outputs
1. Plan and define the programUnderstand what the customer needs and agree the targetsDesign goals, reliability and quality goals, preliminary BOM, preliminary process flow, preliminary special characteristics
2. Product design and developmentComplete and verify the product designDesign FMEA, design for manufacturing and assembly, drawings and specifications, design verification, prototype control plan
3. Process design and developmentDesign the manufacturing process that will make the partProcess flow chart, floor plan, process FMEA, pre-launch control plan, work instructions, MSA plan
4. Product and process validationProve the process on a significant production runProduction trial run, MSA results, initial capability studies, production control plan, PPAP submission
5. Feedback, assessment and corrective actionKeep improving once production startsReduced variation, customer feedback, lessons learned, corrective actions

Key APQP deliverables

The exact list depends on the customer, but most APQP checklists include the following deliverables:

  • Design FMEA (DFMEA): risks in the product design and how they are prevented or detected.
  • Process flow diagram: every step from receiving material to shipping, including rework and inspection.
  • Process FMEA (PFMEA): risks in each process step and the controls in place.
  • Control plan: what is checked, how, how often and what happens when a result is out of specification. Prototype, pre-launch and production versions are usually required.
  • Special characteristics list: the product and process characteristics that affect safety, fit or function.
  • Measurement system analysis (MSA): proof that the gauges used for critical characteristics are good enough.
  • Initial process capability studies: Ppk results for special characteristics.
  • Feasibility commitment: the team's sign-off that the part can be made as designed, at the required volume.

These deliverables are linked. A change to a special characteristic should update the PFMEA, the control plan and the inspection plan together. When they live in separate spreadsheets, that link is easy to break.

How APQP gate reviews work

A gate review is a checkpoint at the end of a phase. The team checks the status of every deliverable, agrees the open risks and decides whether the project can move on.

  1. List every deliverable due at the gate, with its owner and due date.
  2. Rate each one: complete, at risk or late. Many teams use green, yellow and red.
  3. Review open risks and agree actions with owners and dates.
  4. Record the decision: pass, pass with actions, or hold.
  5. Report the status to management and, where required, to the customer.

Gate reviews only work when the status is real. If the team has to collect status from emails and shared folders the day before the meeting, the review becomes a reporting exercise instead of a decision.

APQP and PPAP: how they fit together

APQP is the planning process; PPAP is the evidence package at the end of it. Most PPAP elements, such as the DFMEA, PFMEA, control plan, MSA studies and capability results, are APQP deliverables.

If the APQP project is run well, the PPAP submission is mainly a matter of collecting what already exists. If it is not, the PPAP becomes a last-minute rush to create documents. Our PPAP guide explains the submission itself in more detail.

Common APQP mistakes

  • Starting the PFMEA after the process is already built, so it records decisions instead of shaping them.
  • Keeping the control plan separate from the PFMEA, so controls drift apart over time.
  • Treating gate reviews as status meetings without a clear pass or hold decision.
  • Copying FMEAs from older parts without reviewing what is different.
  • Leaving MSA and capability studies until the week before PPAP.

Running APQP in software

Spreadsheets can work for one or two launches. As the number of projects grows, it becomes hard to see which deliverables are late, which FMEA belongs to which revision, and whether the control plan still matches the PFMEA.

OperaHive APQP software runs each launch through the five phases with owners, due dates and gate reviews. FMEAs and control plans are built in and linked, and the project flows into PPAP so the evidence does not have to be collected twice.

FAQ

Frequently Asked Questions

Still unsure? Ask our team.

What does APQP stand for?

APQP stands for Advanced Product Quality Planning. It is a structured method for planning a new product and its manufacturing process so that the part meets customer requirements from the start of production.

What are the 5 phases of APQP?

The five phases are:

  1. Plan and define the program
  2. Product design and development
  3. Process design and development
  4. Product and process validation
  5. Feedback, assessment and corrective action
Is APQP required by IATF 16949?

IATF 16949 expects a structured product development process, and most automotive customers name APQP in their customer-specific requirements. In practice, an automotive supplier is expected to run APQP for new and changed parts.

What is the difference between APQP and PPAP?

APQP is the planning process that runs through the whole launch. PPAP is the approval package submitted at the end of APQP to show the customer that the process can make good parts consistently.

Who owns APQP in a company?

APQP is owned by a cross-functional team, usually led by a program manager or quality engineer. Engineering, manufacturing, quality, purchasing and often the supplier and customer all own specific deliverables.