Work Order in Simple Terms
A sales order says what the customer wants. A work order (also called a production order or job) tells the shop floor what to make. It is often created by MRP planning, then released to production once material and capacity are available.
What a Work Order Contains
- Part number, revision and quantity to make.
- Start and due dates.
- Materials to issue, taken from the manufacturing BOM.
- The routing: operations, work centres and standard times.
- Inspection points and documents needed at each step.
- Actual results: good quantity, scrap, time used and material lots consumed.
Typical Life Cycle
- Planned: created by MRP or a planner.
- Released: material is checked and the order is sent to the floor.
- In progress: operations are booked as they are completed.
- Completed: finished goods are received into stock.
- Closed: costs and variances are settled.
Example: a work order for 500 pump housings is released on Monday. Machining books 498 good parts and 2 scrapped at operation 20, with casting lot K-552 recorded against the order. When a customer later queries a housing, the order number on its label leads straight to that lot and machine.
Why It Matters
Work orders are where planned and actual production meet. They give the data for yield, cost and on-time delivery, and they are the backbone of traceability. The OperaHive manufacturing execution system coordinates work orders and tracks production output.