MRP in Simple Terms
MRP answers three questions: what do we need, how much, and when? It starts with what must be shipped, explodes that through the BOM into every part and raw material, subtracts what is already in stock or on order, and offsets the result by lead time to show when each purchase or production order must start.
How It Works
- Inputs: the master production schedule or customer orders, the BOM, inventory records and lead times.
- Gross requirements: demand for the finished product is multiplied down through each BOM level.
- Net requirements: stock on hand and open orders are subtracted.
- Planned orders: each shortage becomes a planned purchase, production or subcontract order, released early enough to cover lead time.
MRP is only as good as its data. Wrong BOMs or stock counts give wrong plans.
Example
A customer orders 500 valves for week 10. Each valve needs 2 O-rings. The plant has 300 O-rings in stock and none on order, so it needs 1,000 minus 300, or 700 more. With a supplier lead time of 3 weeks, MRP creates a planned purchase order for 700 O-rings to be placed by week 7.
Why It Matters
- Fewer shortages that stop production.
- Less excess stock bought too early.
- Purchasing and production work from one shared plan.
Many plants use MRP for planning and kanban for daily replenishment of high-volume parts. OperaHive MRP software calculates material requirements, identifies shortages and supports make, buy and subcontract decisions.